Shocking: Eirgrid cancel plans for new overhead electricity lines – TheLiberal.ie – Our News, Your Views

Shocking: Eirgrid cancel plans for new overhead electricity lines




1365927_01e4129d

Eirgrid has announced that their proposed plans for an overhead 400KV line from Cork to Kildare will not go ahead.

Instead, the company plans on pursuing a regional option, which uses a technology, known as “series compensation”, which enables more power to flow through existing lines, and so does not require the installation of new overhead lines.

It proposes to use the existing 400kv grid infrastructure from Moneypoint to the greater Dublin area to deliver more services, instead of constructing any new overhead solutions for Grid Link.

However, a new underwater cable across the Shannon estuary is required in addition to some upgrade works to existing transmission lines.

The controversial Grid Link project had encountered stiff opposition from anti-pylon groups throughout the course of its planning.

An Independent Expert Panel had been contracted to oversee the integrity of the project undertaken by EirGrid to report on the Grid West and Grid Link projects.

Earlier this year, an Eirgrid discussion paper introduced the “regional option”, which was not previously known by the panel.

In a statement the panel said as its Terms of Reference do not extend to consideration of the “Regional Option” the overhead and underground cable options are not needed and it said any comments it would make would be out of date.

Share this story with a friend

Share this story

Tell us what you think on our Facebook page